Structural Remodels

Load-Bearing Wall Removal & Structural Openings

Opening a room is easy on a sketch. The real work is tracing the load path and providing a buildable support system.

Start with the load path

Before a wall is removed, the existing roof, ceiling, floor and foundation conditions have to be understood well enough to determine how the loads will be transferred. Depending on the project, field investigation or selective demolition may be needed.

Existing conditions

Document wall location, framing direction, supports and relevant concealed conditions as available.

Engineering

Coordinate beam, post, connection and support design with a Florida-licensed engineer when required.

Permit documents

Integrate the structural solution into the remodel plan set so the field work is coordinated.

Concealed conditions matter

No drawing should pretend to know what is behind every finished surface. Where framing, foundations or connections cannot be confirmed, the plans should identify field-verification requirements and provide a process for addressing unexpected conditions.